Building Process.
Typical Construction Time
HOMES UP TO 3000 SQ FT
6 MONTHS FROM CONSTRUCTION START
HOMES 3000-5500 SQ FT
7+ MONTHS FROM CONSTRUCTION START
HOMES 5500+ SQ FT
9+ MONTHS FROM CONSTRUCTION START
Design Phase (2 weeks)
Develop design criteria and subdivision requirements (if applicable)
Draw floor plan or select an existing plan
Draw roof plan, elevations, electrical plans, and site plan
Obtain loan pre-approval
Contract & Specifications (2 weeks)
Specify unique products or features to be used in home
Determine pricing on home based on plan design and features
Sign contract
Pre-Construction (6 weeks)
Submit contract documents to lender for construction loan
Geotechnical reports on soil
Foundation engineering
HOA Submittal
Obtain permits…..(City of Houston – add 45 days) (City of Conroe – add 15 days)
Construction
Site preparation / foundation
Framing and mechanicals
Drywall, trim carpentry, cabinets
Completion of Flooring, paint, and fixtures
Landscaping and final clean-up
Final walk / move-in
Permanent Loan Processing (45 days)
Submit contract documents to lender for permanent loan
Survey property
Appraise project
Closing documents