Typical Construction Time

HOMES UP TO 3000 SQ FT

6 MONTHS FROM CONSTRUCTION START

Blanco casa del ladrillo

HOMES 3000-5500 SQ FT

7+ MONTHS FROM CONSTRUCTION START

1. MODELO.JPG

HOMES 5500+ SQ FT

9+ MONTHS FROM CONSTRUCTION START

Propiedad privada

Design Phase (2 weeks)

Develop design criteria and subdivision requirements (if applicable)

Draw floor plan or select an existing plan

Draw roof plan, elevations, electrical plans, and site plan

Obtain loan pre-approval

Contract & Specifications (2 weeks)

Specify unique products or features to be used in home

Determine pricing on home based on plan design and features

Sign contract

Pre-Construction (6 weeks)

Submit contract documents to lender for construction loan

Geotechnical reports on soil

Foundation engineering

HOA Submittal

Obtain permits…..(City of Houston – add 45 days) (City of Conroe – add 15 days)

Construction

Site preparation / foundation

Framing and mechanicals

Drywall, trim carpentry, cabinets

Completion of Flooring, paint, and fixtures

Landscaping and final clean-up

Final walk / move-in

Permanent Loan Processing (45 days)

Submit contract documents to lender for permanent loan

Survey property

Appraise project

Closing documents